CMA CMA InternationalAayan Technical Co. Ltd · Jeddah
Start an enquiry
Contract guidance

The bill of quantities.

A Bill of Quantities (BOQ) is an itemised schedule of the measured work in a project — each item described, quantified in its own unit, and priced with a rate and a total. It converts a set of drawings into a number that can be compared, valued and paid against.

01Bills of quantities

The BOQ is the only document that makes two fit-out prices comparable. Understanding what is inside it is how you stop paying twice for the same thing.

  1. Preliminaries

    Site establishment, supervision, temporary works, protection, access, permits, insurance and the cost of simply being on site for the duration. Bidders who under-price preliminaries recover them through variations.

  2. Measured work by trade

    Civil, mechanical, electrical, plumbing, fabrication, joinery, façade and finishes, each measured in its proper unit — square metres, linear metres, numbers or item.

  3. Provisional sums

    An allowance for work that is known to be needed but not yet designed. It is expended against actual cost, so a bid full of provisional sums is not a fixed price.

  4. Prime cost items

    An allowance for a supplied item whose supplier is not yet chosen — a floor finish, a light fitting, a sanitaryware range. The contractor prices the installation, not the item.

  5. Dayworks

    Rates for labour, plant and material used on instructed work that cannot be measured. Check them at tender: they are the rates you will be charged when something changes.

  6. Contingency

    A client-held allowance for the unknown. It belongs to the client, not the contractor, and is released only on instruction.

02Questions

Bills of quantities —
straight answers.

What is the difference between a provisional sum and a prime cost item?

A provisional sum covers work that has not been designed yet. A prime cost item covers a supplied product whose make and model has not been chosen yet. Both are placeholders, and both convert to actual cost when instructed.

Why are two fit-out BOQ totals so different?

Usually because the bidders measured different quantities, made different assumptions about the base-build condition, or excluded different scope. Compare the rates item by item before you compare the totals.

Who prepares the BOQ on a fit-out project?

On a larger project, the client's quantity surveyor. On a single retail unit, the contractor commonly measures from the drawings and submits their own BOQ — which also shows you how carefully they read them.

Is a BOQ price a fixed price?

Only for the measured items, and only if the scope does not change. Provisional sums, prime cost items and contingency are all expended against actual cost, so the tender total is a forecast for those lines.

What is the most commonly under-priced BOQ section?

Preliminaries, followed by builder's work in connection with services — the cutting, chasing, forming and making good that every other trade depends on and no trade wants to own.

03More on contracting

We bid retail and commercial fit-out tenders across the Gulf from our Jeddah base.

Send the tender documents