CMA CMA InternationalAayan Technical Co. Ltd · Jeddah
Start an enquiry
Contract guidance

How to tender a fit-out contract.

A fit-out tender is the process of issuing a defined scope to a shortlist of contractors and comparing their priced, programmed responses on identical terms. The comparison is only meaningful if every bidder priced the same scope, the same specification and the same handover date.

01Running a tender

A fit-out tender is won or lost in the documents you issue, not the ones you get back. Here is the pack that gets you comparable bids.

  1. Fix the scope before you issue

    Decide what is landlord's work, what is base build and what is your fit-out. Ambiguity here is where variations are born. A one-page scope-split matrix costs an hour and saves a month.

  2. Issue a complete document set

    Architectural and MEP drawings, brand fit-out manual, landlord or mall handbook, the base-build handover condition, the target handover date and the form of contract you intend to use.

  3. Give every bidder the same site access

    One organised site visit with all bidders present, and one written Q&A circulated to everyone. Private clarifications produce bids you cannot compare.

  4. Ask for the bid in a fixed format

    A priced BOQ against your schedule, a dated programme, a method statement, material submittals, an HSE plan and the company/legal pack. Free-format quotations cannot be levelled.

  5. Level the bids before you rank them

    Strip out qualifications and exclusions, add back what each bidder omitted, then compare. The cheapest raw number is very rarely the cheapest contract.

  6. Interrogate the programme, not just the price

    Ask each bidder which approval sits on their critical path and what happens if it slips a week. The answer tells you who has actually built in your mall before.

  7. Award on scope, programme and covenant together

    Check the Commercial Registration, insurance certificates and trade licence are current, and that the entity bidding is the entity that will sign.

02Questions

Running a tender —
straight answers.

How long should a fit-out tender period be?

Two to three weeks for a single retail unit with a complete document set; four or more for a multi-unit rollout or where the base-build condition is uncertain. Shorter than two weeks and you get padded, heavily-qualified prices rather than a considered bid.

How many contractors should I invite to a fit-out tender?

Three to five. Fewer than three gives you no comparison; more than five and quality bidders discount the odds of winning and put less effort into the bid.

What makes two fit-out bids impossible to compare?

Different scope splits with the landlord, different assumptions about the base-build handover condition, different exclusions, and different programmes. Level all four before you rank anything.

Should I issue a Bill of Quantities or let bidders measure?

Issue one if you have it — it forces like-for-like pricing. If you do not, ask each bidder to submit their own measured BOQ, which also shows you who actually read the drawings.

What is the single most common cause of fit-out delay?

Approvals. Shop drawings, material submittals and mall or authority NOCs run in sequence instead of in parallel. Ask every bidder how they intend to run them concurrently.

03More on contracting

We bid retail and commercial fit-out tenders across the Gulf from our Jeddah base.

Send the tender documents